We attended our Review 3 on 24-Feb-2012. Mrs. Kavitha and Other CSE staffs are gathered to judge our project. We started to explain our project with very scarred. Although, we explained our project and we also described the modules which are included in our project.
Sunday, February 26, 2012
Wednesday, February 22, 2012
Modules for Project
It is very expensive to implement this spider web topology as a Graduation Project. So we decided to concentrate on Network Administration Part. In future, we may develop this project by implementing it with routers and switches.
We are using 2 main modules and 8 sub-modules which are categorized according to the LINK STATE ROUTING ALGORITHM.
Link State Routing Algorithm:
- Knowledge about the neighborhood.
- Routing to the whole network.
- Information Sharing when there is a change in network.
Modules:
The modules for this project are shown below.
- Login
- Admin Console
- File Transfer - Server
- File Transfer - Client
- Network Scan
- Monitor IP (ARP Spoofing Technique)
- IP Database
- IP Route Tracing (Shortest Path Analysis)
- Chat Server
- Chat Client
Login and Admin Console are the 2 main modules and others are sub modules for the Admin Console module.
Modules vs Link State Routing Algorithm:
- Knowledge about the neighborhood:
File Transfer - Server, File Transfer - Client
- Routing to the whole network:
Monitoring IP, IP Database, Network Scan, IP Route Tracing
- Information Sharing when there is a change:
IP Routing, IP Database, Chat Server, Chat Client
Tuesday, February 21, 2012
Project Review 1 and Review 2
The first review of our project was conducted on 27, December 2011. We prepared a power point presentation for our project. We are judged by Mrs. Kavitha - Batch Councellor (Primrose Batch), PITS. We also planned our project time management. We estimated that we will complete our project on 26, February 2012.
In second review of our project, we explained the project core concept and what are the process are going to be done in this project.
In second review of our project, we explained the project core concept and what are the process are going to be done in this project.